Schedule Tab Project Management>Project Central

Top  Previous  Next

Overview

 

One of the most powerful sections of this applet, the Schedule tab give the Project Manager real time access to Resource allocation and schedules for the selected project.

 

ProjectCentralSchedule

 


 

Field Descriptions

 

Schedule Toolbar

 

Add Resource - Launches the Schedule Labor dialogue

 

ProjectCentralLaborScheduler

 

Day/Week/Month - Groups the Schedule accordingly
WBS Filter - Filters the Schedule by WBS level

 

Schedule Interface

 

Reflects scheduled resources for the selected project. Resources can be reallocated dynamically by moving, increasing or decreasing the allocated time. Clicking the listed employee will display the employee's availability chart below.

 

Scheduled / Availability Detail

 

This chart reflects each employees scheduled time based on project allocation.