Upload a PM Report Utilities>PM Report Designer

Top  Previous  Next

Overview

How to Upload a PM Report.

After modifying a layout, it must be uploaded into the database to be put in use.


Step 1 - Click the Upload button (fig. 1). Use the File Navigator that appears to locate the modified design (RDL extension). See fig. 2.

Upload a Report1

(Fig.1)

 

Download a Report2

(Fig.2)

 

Step 2 - Select the folder to upload. Click OK to upload the design. Next, click OK, and the folder has been uploaded.

Note: A warning will appear if the name of the RDL does not match the name of the report design. The warning can be ignored. It is meant to prevent accident uploads into the wrong report.