Gantt Project Management>Project Planning

Top  Previous  Next

Overview

 

Project Planning's Gantt chart allows you to plan project tasks, order-of-work and gives you feedback on the impact of scheduled items- including Critical Path. Launched from the toolbar in Project Planning, a project's schedule is displayed in an interactive Gantt chart.

 

Use the Gantt to schedule each phase/task of the project based on start/finish dates or duration. Once set, these dates control the time frames in which you can schedule resources through Project Planning. As you build the schedule, use the Gantt bars to adjust schedules as appropriate. Clicking a phase/task in the WBS Grid re-centers the Chart.

 


 

Tutorial

1.Browse to PM>Project Planning
2.Load/Create the project you wish to work with
3.Click Gantt from the toolbar. The Gantt dialogue will launch.
4.Select a View Option
5.Schedule the WBS beginning with Start Dates
6.Add Finish Dates by increasing/decreasing Duration or adding a static Finish date
7.Use Predecessors (description below) to link WBS nodes together for ordered/hierarchical scheduling
8.Adjust schedules using the WBS Grid or by dragging the Gantt Bars displayed on the Gantt Chart
9.Click Save

 


 

Field Descriptions

View Options

Days, Weeks, Months, Quarters, Years - The Gantt chart can be viewed in units of Days, Weeks, Months, Quarters or Years. Change the view by clicking the corresponding button. When viewing in Days or Weeks, the current date is highlighted on the chart.
Show Critical Path - Displays Critical Path by color-coding the Gantt. InFocus calculates Critical Path by taking the longest path to the end of the project.
Customize Settings - Sets custom user settings for viewing Gantt information
oBar Settings
Color - Default bar color
Date/Time Format - Format to use for display text
Height - Sets the height for bar rows
Inside Text - Text to display on the bar
Left Text - Text to display to the left of the bar
Right Text - Text to display to the right of the bar
Show Tooltip - When checked, hovering over the bar will display a tooltip
Text Color - Bar text color
oCritical Path
Critical Path Color - Color for displaying critical path
oGrid Settings
Row Height - Sets the height for grid rows

 

WBS Grid

Description - The WBS Grid displays the project structure and associated planning. Each node can be scheduled and ordered using the fields contained in the grid.

Index - Index of the project node, primarily used for assigning predecessors (see below).
WBS - Project Path (read only)
Name - Project Name (read only)
Duration - Increase or decrease the amount of time allotted to a project node in increments of days or weeks (based on the selected view option). This updates associated Finish dates and Gantt Bars. Project Level duration is summarized and reflected in the number of planned days- start to finish.
Start - Planned start date
Finish - Planned end date
Predecessors - Indicated by the Index number, predecessors allows you to control, for instance, the schedules for a list of tasks underneath a project phase. Using a predecessor, you can effectively lock the schedules of a WBS together- rescheduling the predecessor has a ripple effect on the schedules of the linked nodes. The nature of the relationship between a predecessor task and a successor task determines the type of task dependency to use. This relationship can be defined by typing the following codes into the Predecessors column prefixed by the Index ID (e.g. 2FS):
oFS (Finish-to-Start): Task A must finish before Task B can start. This is very commonly used and the default dependency created if only an Index ID is entered into the Predecessors column.
oSS (Start-to-Start): Task B can’t start until Task A starts. Task B can begin any time after Task A begins. This method can be beneficial as it can help reduce the overall duration of the project as it allows for task overlap.
oFF (Finish-to-Finish): Task B can’t finish until Task A is done. They don’t have to end at the same time- Task B can end any time after Task A ends. Similar to SS, FF dependencies can also reduce the overall duration of a project.
oSF (Start-to-Finish): Task B cannot finish until the start of Task A. This is a VERY RARE scenario of Task in any type of Project.

 

Chart

The chart is reactive to the view options and the WBS Grid settings and displays two types of bars: Gantt bars and a Summary bar.

Gantt Bars - Gantt bars (blue) reflect the settings of the associated project node listed in the WBS chart. Gantt Bars can be moved by editing the WBS chart or by clicking and dragging the Gantt bar. This will adjust any associated schedules. You can alter the duration (and subsequently start and end dates) of a task by gripping the left or right edge of the Gantt bar and increasing or decreasing its length.
Summary Bar - The summary bar shows a running total of the time represented by all scheduled tasks. While Gantt bars can be edited, the Summary bar is read only.

 

Other Options

Print - Launches print preview for content of the Gantt Chart and WBS Grid
Automatically move Schedules with Start Date - When checked, Start Dates are impacted when sliding Gantt Bars
Save - Saves Gantt information
Save & Close - Saves Gantt information and closes the Gantt window
Close - Closes the Gantt window without saving