Overview

The Auto Schedule utility is an easy way to schedule a single resource over selected time slots.

 


 

Field Descriptions

Resource - Name of the Resource. Generic is used if none is selected.
Allocation - Name of Allocation. Generic is used if none is selected.
Start Date - Start Date of the selected cells.
End Date - End Date of the selected cells.
Total Days - Total days that have been selected.
Schedulable Days within Weeks - Number of days within the weeks that can be scheduled on. This is affected by the Allowable Days checked on the Planning Preferences. More on Planning Preferences
Calculator - Tool that assists in calculating the hours and amount.

 

Options

A - Automatic Assignment. Automatically assigns the Hours/Units and Amount to each schedulable day in the range.
M - Manual Assignment. Manually assigns the Hours/Units and Amount to the days in the range. This is affected by the Allowable Days checked on the Planning Preferences. More on Planning Preferences
%B - Percentage of Budget - Enter a percentage of the Budgeted amount to  assigns the Hours/Units and Amount to each schedulable days in the range. Enter 25 for 25%.
%A - Percentage of Allocation - Enter a percentage of the Allocated amount to  assigns the Hours/Units and Amount to each schedulable days in the range. Enter 25 for 25%.