Earned Value Project Management>Project Planning

Top  Previous  Next

Overview

Earned Value is an approach where you monitor the project plan (budget), actual work, and percent completed value to see if a project is on track. Earned Value shows how much of the budget and time should have been spent, considering the amount of work done so far.

 


 

Key Concepts

Budget – The budget is the sum of the budgeted dollars for the project over time. This is calculated from the Resource Schedule (Project Planning applet) . Alternatively, if you do not want to build the schedule to determine the budget, you can enter the start and end date with a respective budget amounts at the lowest levels of the project and use the “Spread Budget by WBS Start/End date” option in the EVM pop up window.
Actuals – The actuals come from the Timesheets. You can optionally include both unsubmitted and unapproved time.

 

Field Descriptions

Header

Spread Budgets by WBS Start / End Dates - When checked, the budgets are spread throughout the chart using the start and end dates on the project WBS.
Period Type - Time increment that you would like the Earned Value chart to display in. Options are Day, Week, Two Week, Four Week, Thirty Day, Month and Year.
Name - Left window displays the Project Name for easy navigation.

 

Budgets (PV) - Planned Value

Include Labor - When checked, Labor Budgets will be included in the Planned Value (PV) figures.
Include ODC - When checked, ODC Budgets will be included in the Planned Value (PV) figures.
Include OCC - When checked, OCC Budgets will be included in the Planned Value (PV) figures.
Include ICC - When checked, ICC Budgets will be included in the Planned Value (PV) figures.

 

Actuals (AC) - Actual Cost

Include Unsubmitted - When checked, unsubmitted time will be included in the Actual Cost (AC) figures.
Include Unapproved - When checked, Unapproved time will be included in the Actual Cost (AC) figures.

 

Percent Complete (EV) - Earned Value

Use Only Labor - When checked, only labor will be used when calculating the Earned Value (EV) figures.

 

Show

Description - When checked, the following items will show in the Earned Value grid.

Budget (PV)
Budget Current
Scheduled Variance (SV)
Scheduled Performance Index (SPI)
Earned Value (EV)
Earned Value Actual
Cost Variance (CV)
Cost Performance Index (CPI)
Actual Cost (AC)