Overview
The Resource Projections Utility is used to aggregate and analyze schedule data from project planning.
Key Concepts
• | Scheduled hours can be viewed by employee or job title and compared against available hours to show predicted utilization. Hours are scheduled through Project Planning. More on Project Planning |
• | Clicking on Used columns will cause a drill-down screen to pop up, displaying the distributions of the hours among the scheduled projects. |
Additional Toolbar Options
Aside from the standard toolbar options this applet has the following options:
• | View - Additional View options |
o | Balance Column - When selected, a Balance column appears in the Resource Projections grid. |
• | Export - The Export button gives the user the ability to export the projections to Excel. |
|